Bridge Scoping Unit
Goal
The goal of this document is to describe the basic bridge scoping processes and components, and how the project manager and districts will interact with the Bridge Office during project scoping. This has two distinct sections: (1) new or replacement bridge projects, (2) repair bridge projects.
Products the unit provides
New or replacement bridge projects
- Completed Form B – Example Completed Form B
- New or replacement bridge scoping recommendations
- Conceptual Sketch
- Scoping cost estimate
Bridge repair projects
What to expect from the unit
New or replacement bridge projects
- The products listed above
- Coordination between the bridge preliminary, bridge hydraulics, bridge estimating units to accurately complete the Form B
Bridge repair projects
- The products listed above
- Coordination between the bridge office staff, district bridge scoping engineer (D1, D3, D6, D7, Metro) and district bridge engineer
What you need to provide to the unit
New or replacement bridge projects
- Completed Form A (Example Completed Form A)
- Completed Phase 2 ABC form – Need to complete if the Bridge inventory form shows Accelerated Bridge Construction (ABC) is a possibility, Potential ABC = Yes
Bridge repair projects
What the unit expects from you
New or replacement bridge projects
- Coordination with bridge scoping to complete scoping prior to the project entering the STIP
- The items listed above
- Prompt follow-up to any questions or clarifications on scoping requests
- Any box culvert scoping cost estimates, the Bridge Office does not complete box culvert cost estimates, those need to be done by the District
- Appropriate project schedule information and due date expectations
Bridge repair projects
- Coordination with bridge scoping to complete scoping prior to the project entering the STIP Coordination between the bridge office staff and district bridge engineer
- The items listed above
- Prompt follow-up to any questions or clarifications on scoping requests
- Appropriate project schedule information and due date expectations