Environmental process | Environmental review | Scoping Decision Document
Scoping Decision Document process
Format and content
MEQB rules do not specify a format for the Scoping Decision Document. At a minimum, the SDD addresses the following points:
- The issues to be addressed in the EIS
- Time limits for preparation (If shorter than allowed by Minnesota Rule parts 4410.0200 to 4410.6500)
- Identification of the permits for which information will be gathered concurrently with EIS preparation
- Identification of the permits for which a record of decision will be required
- Alternatives that will be addressed in the EIS
- Identification of potential impact areas resulting from the project itself and from related actions which shall be addressed in the EIS
- Identification of necessary studies requiring compilation of existing information or the development of new data that can be generated within a reasonable amount of time and at a reasonable cost
Typically, the DSDD and SDD also describe the:
- Report Purpose
- Project Description
- Responsible Governmental Unit and Project Manager
- The issues and alternatives that will not be addressed in the EIS, as determined through scoping process
The final SDD, which is issued after conclusion of the scoping comment period, also addresses:
- Comments that were received during the scoping comment period
- Additional information relevant to the Scoping Decision that became available after the release of the SD/DSDD
The Scoping Document (SD) provides complete details about the scoping process. The Scoping Decision Document (DSDD and SDD) is more concise, focused on the decisions that resulted from the scoping process, specifically what issues and alternatives will be addressed in the EIS.
Processing/circulation
The Draft Scoping Decision Document (DSDD) is developed and circulated at the same time as the Scoping Document (SD). See Scoping Document TPDP chapter for processing/circulation details. The following steps are for the final Scoping Decision Document (SDD).
- District develops Scoping Decision Document.
- Develops preliminary final Scoping Decision Document, updating the Draft Scoping Decision Document (DSDD) to reflect information gathered during public comment period, in consultation with the Office of Environmental Stewardship (OES) and FHWA
- TPDP/Scoping/Reports/EIS
- Develops preliminary final Scoping Decision Document, updating the Draft Scoping Decision Document (DSDD) to reflect information gathered during public comment period, in consultation with the Office of Environmental Stewardship (OES) and FHWA
- District distributes copies to Central Office and FHWA for review.
- For signature blocks, see Who Approves Project Documents
- For guidance on FHWA review, see FHWA and MnDOT Stewardship and Oversight Agreement
- Reviewers provide comments to District.
- Complete within 45 days of receiving preliminary report
- OES coordinator returns comments to Project Manager with copy to FHWA. FHWA Area Engineer returns FHWA comments to MnDOT Project Manager with copy to OES
- CO State-Aid (required only if local agency is involved and using federal aid funds) returns comments to Project Manager with copy to OES/FHWA
- District revises Scoping Decision Document based on comments received. District Engineer signs signature page.
- District submits revised final Scoping Decision Document to OES for approval (one copy and one signed signature page).
- OES approves the Scoping Decision Document:
- Conducts final review of Decision Document (review completed in 5 days)
- Approves Document: Chief Environmental Officer signs signature page (once all comments are adequately addressed)
- Returns original-signature page to District for project file
- The approved SDD must be stored in eDOCs
- District distributes copy of signed Scoping Decision Document:
- FHWA: Two hard copies and one signed electronic copy
- CO State Aid: (required only if local agency is involved and using federal aid funds): One hard copy and one signed electronic copy
- A summary of the Scoping Decision is included in the state EIS preparation notice that is published in the EQB Monitor
- A summary of the Scoping Decision is included in the state EIS preparation notice that is published in the EQB Monitor.