Route (Hwy or Interstate) |
Description |
Begin date |
End date |
Total cost |
2025 construction cost |
Website |
Hwy 9, I-94 |
Guardrail repair along Hwy 9 and I-94 |
May 2025 |
June 2025 |
$531,000 |
$531,000 |
None |
Hwy 10 |
Construct railroad underpass on Hwy 10/75 at 11th Street in Moorhead |
March 2024 |
November 2026 |
$114.7 million |
$55 million |
mndot.gov/d4/projects/moorhead11thstunderpass |
Hwy 29 |
Improve access and pedestrian safety in Alexandria on 3rd Ave |
July 2025 |
October 2025 |
$900,000 |
$900,000 |
mndot.gov/d4/projects/hwy293rdave |
Hwy 59, Hwy 108 |
Complete streets reconstruction on Hwy 59, and Hwy 108 in Pelican Rapids; resurface bridge |
May 2024 |
October 2025 |
$22.77 million |
$9.5 million |
mndot.gov/d4/projects/pelicanrapids |
Hwy 59, I-94 |
Restripe edgeline on Hwy 59 north of Mahnomen and I-94 from Barnesville to Rothsay |
June 2025 |
July 2025 |
$850,000 |
$850,000 |
None |
Hwy 78, Hwy 79 |
Chip seal Hwy 78 from I-94 to Battle Lake, and Hwy 79 from Elbow Lake to Evansville |
May 2025 |
August 2025 |
$1.9 million |
$1.9 million |
None |
I-94 |
Resurface the Red River Bridge in Moorhead |
April 2025 |
August 2025 |
$5.6 million |
$5.6 million |
None |
I-94 |
Install fiber communications, digital message boards, and cameras along I-94 in Moorhead |
May 2025 |
June 2026 |
$2.86 million |
$2.86 million |
mndot.gov/d4/projects/moorhead-its |
I-94 |
Upgrade existing Lake Burgen Rest Area buildings and improve site amenities to meet modern standards, construct new rest area building, improve accessibility and safety |
October 2025 |
February 2027 |
$6.5 million |
$1.5 million |
mndot.gov/d4/projects/burgenlake |
I-94 |
Replace EB bridges over CP rail and CR 23 near Alexandria |
April 2024 |
August 2025 |
$32.4 million |
$6 million |
mndot.gov/d4/projects/alex94bridges |
I-94 |
Replace WB I-94 bridge over Pelican Creek near Ashby |
June 2024 |
September 2025 |
$6.7 million |
$3.35 million |
mndot.gov/d4/projects/94bridges-pelicancreek |
I-94 |
Resurface EB I-94 from west of CR 11 near Rothsay to east of Hwy 59 near Fergus Falls |
May 2025 |
November 2025 |
$22 million |
$22 million |
mndot.gov/d4/projects/94rothsay-ff |
Hwy 108 |
Slurry seal on Hwy 108 in Henning, storm sewer repairs |
July 2025 |
August 2025 |
$96,000 |
$96,000 |
mndot.gov/d4/projects/henning |
Hwy 113 |
Replace signs on Hwy 113 from Mahnomen county line to Hwy 71 |
June 2025 |
July 2025 |
$541,000 |
$541,000 |
None |
Hwy 114 |
Construct roundabout at Hwy 114/Hwy 27 intersection; replace and repair culverts from Hwy 55 near Lowry to I-94 |
May 2025 |
October 2025 |
$3.2 million |
$3.2 million |
mndot.gov/d4/projects/hwy114lowry-94 |
Hwy 210 |
Resurface Hwy 210 from Hwy 29 to west of Hwy 71 near Hewitt |
July 2025 |
September 2025 |
$4.8 million |
$4.8 million |
mndot.gov/d4/projects/hwy210-hewitt |