Route (Hwy or Interstate) |
Description |
Begin date |
End date |
Total cost |
2025 construction cost |
Website |
Hwy 12 |
Resurface and repair Hwy 12 from Litchfield to Darwin; upgrade sidewalks to improve accessibility; replace culverts |
July 2024 |
October 2025 |
$9.5 million |
$4.45 million |
mndot.gov/d8/projects/hwy12litchtocokato |
Hwy 14 |
Repair slope on Hwy 14 in Balaton near Lake Yankton |
August 2025 |
August 2025 |
$400,000 |
$400,000 |
None |
Hwy 19 |
Reconstruct Hwy 19 from Marlene Street through Bruce Street intersection in Marshall; install roundabout at Country Club Drive; install EV charging station at Avera parking lot; upgrade sidewalks and ramps |
May 2025 |
October 2026 |
$26.9 million |
$13 million |
mndot.gov/d8/projects/hwy19marshall |
Hwy 23 |
Construct left-turn lane on Hwy 23 at CR 1, northeast of Raymond |
April 2025 |
July 2025 |
$1.34 million |
$1.34 million |
mndot.gov/d8/projects/hwy23raymond-hwy71svea |
Hwy 23 |
Install trees along Hwy 23 from CR 6 in Hawick to Paynesville |
October 2024 |
June 2025 |
1.5 million |
$855,000 |
mndot.gov/d8/projects/hwy23southgap |
Hwy 23 |
Resurface two bridges on Hwy 23, 43 and 61 miles north of Hwy 19 in Marshall |
May 2025 |
October 2025 |
$1.7 million |
$1.7 million |
mndot.gov/d8/projects/hwy23greenvalley |
Hwy 23, Hwy 71 |
Resurface SB lane of Hwy 71 from south end of Hwy 23 bypass to the Business 71 split in Willmar; resurface Hwy 23 from CR 5 to start of Hwy 23 bypass in Willmar |
August 2025 |
November 2025 |
$21 million |
$400,000 |
mndot.gov/d8/projects/hwy71-23willmar |
Hwy 40 |
Construct left- and right-turn lanes between CR 55 and CR 5 in Willmar |
July 2025 |
August 2025 |
$1.12 million |
$1.12 million |
mndot.gov/d8/projects/hwy40willmar |
Hwy 52 |
Improve or replace four pedestrian bridges statewide, and improve accessibility. Locations include the bridges spanning Hwy 212 from DeSoto Ave to 5th St E in Glencoe; Hwy 52 from Lewis St to Stickney Ave in South St Paul; I-35E from Pleasant Ave to Thompson St in St Paul; I-35 between Michigan Ave and Railroad St in Duluth |
April 2025 |
October 2026 |
$11.2 million |
$6 million |
None |
Hwy 67 |
Install lighting at Hwy 67 and CR 6 and at Hwy 67 and CR 21 |
May 2025 |
May 2025 |
$90,000 |
$90,000 |
mndot.gov/d8/projects/hwy67granitefallstoecho |
Hwy 71 |
Install left-turn lane on Hwy 71 at Kandiyohi CR 3 in Svea |
April 2025 |
July 2025 |
$1.3 million |
$1.3 million |
mndot.gov/d8/projects/hwy23raymond-hwy71svea |
Hwy 212 |
Install traffic crossovers on Hwy 212 1 mile west of CR 9 near Plato in preparation for a future bridge replacement project |
August 2025 |
October 2025 |
$290,000 |
$290,000 |
mndot.gov/d8/projects/hwy212plato |
Various roads in MnDOT District 8 |
Repair culverts on multiple highways districtwide |
May 2025 |
October 2025 |
$4.4 million |
$4.4 million |
mndot.gov/d8/projects/districtwide-culverts |
Various roads in MnDOT District 8 |
Perform bridge maintenance on multiple bridges districtwide |
July 2025 |
August 2025 |
$200,000 |
$200,000 |
None |
Various roads in MnDOT District 8 |
Install centerline rumble strips on multiple concrete roadways districtwide |
August 2025 |
September 2025 |
$1.9 million |
$1.9 million |
None |
Various roads in MnDOT District 8 |
Install striping on multiple highways districtwide |
June 2025 |
October 2026 |
$570,000 |
$570,000 |
None |